Dear Valued Customer

We have a request for Power Shutdown Maintenance from SP Group on incoming High Tension Switchgear. The maintenance details as follows:

Power Source B – High Tension Switchgear Maintenance
Date of maintenance : 20th March 2021
Start Date & Time : 20th March 2021 (Sat) 08:00 SGT Local Time
End Date & Time : 20th March 2021 (Sat) 15:00 SGT Local Time
Reason : Maintenance of High Tension Panel
Impact : Genset will start up to support power source B during this maintenance. There should be minimum impact on IT load. Power source A will be available during this period to support your racks
** SGT means Singapore Time (+8 UTC/GMT)

Power Source A – High Tension Switchgear Maintenance
Date of maintenance : 24th April 2021
Start Date & Time : 24th April 2021 (Sat) 09:00 SGT Local Time
End Date & Time : 24th April 2021 (Sat) 15:00 SGT Local Time
Reason : Maintenance of High Tension Panel
Impact : Genset will start up to support power source B during this maintenance. There should be minimum impact on IT load. Power source B will be available during this period to support your racks.
** SGT means Singapore Time (+8 UTC/GMT)

Details about the maintenance we will update more in the shortest time. In case you need further assistance, please contact us via the following channels:

Ticket: https://support.centerhop.com/en
Email: support@centerhop.com

Once again, thank you for your trust and look forward to your cooperation in this maintenance.